181212 | St Erth Multi Modal Hub – key milestones update for residents

Via St Erth Parish Council Website

Key points:

  1. A30 junction is planned to go live in early March
  2. The platform extension is planned to be completed prior to the timetabling change in May
  3. The Station building is now complete
  4. The Car Parks will be fully operational in time for the timetabling change in May but hoped that the majority of the construction activities will be finalised in early April.

 


 

St Erth Multi Modal Hub – key milestones update for residents

This is the latest update from Kieren Couch of Ward Williams Associates – Civil Project Manager for St Erth Multi Modal Hub (a.k.a. St Ives Park and Ride)

1. A30 junction is planned to go live in early March
2. The platform extension is planned to be completed prior to the timetabling change in May
3. The Station building is now complete
4. The Car Parks will be fully operational in time for the timetabling change in May but hoped that the majority of the construction activities will be finalised in early April.

 

 

Book page

TitleCreated
2026-EXTENDED-17th April 2026 to 22nd April- Resurfacing Steamers Hill; Hatchs Hill; Angarrack Lane | 1 Apr 07:30 - 17 Apr 23:59 7 hours 23 min agoBook page
2026-April-POSTPONED-planned improvements i.e. install footpath, paint double yellow lines junction Grist Lane Hatchs Hill 3 days 20 hours agoBook page
2026 - Resurfacing Steamers Hill; Hatchs Hill; Angarrack Lane | 1 Apr 07:30 - 17 Apr 23:59 2 weeks 1 day agoBook page
250330; Closure order:30 Mar-17 Apr 2026; 07:30-17:00; Clearway Parking Zone; Hatchs Hill, Steamers Hill and Angarrack Lane 3 weeks 3 days agoBook page
Traffic/Roads - Marsh/Grist Lane - Traffic counts 2019 onwards 15 weeks 14 hours agoBook page
Approved with conditions | PA25/07094 | First floor extension over existing garage to create Art studio with guest bedroom... 19 weeks 3 days agoBook page
PA25/07094 | First floor extension over existing garage to create Art studio with guest bedroom, covered parking area below | As 20 weeks 2 days agoBook page
251027 | 20mph Monitoring—Hayle & St Ives Speed Data; Phase 3a-May-Jun 24 v Sep-Oct 24; Steamers Hill; Gwinear;Carbis;Nancledra 24 weeks 2 days agoBook page
PA25/07184 | Retention of 4no. existing holiday pods, swimming pool, incidental building, extended driveway and annexe converted 24 weeks 5 days agoBook page
251009 | Stark reality of life in Cornwall revealed through 2025 Vital Signs Report 26 weeks 6 days agoBook page
251010 | Cornwall backs 20mph rollout; St Austell's the only town to reject the plans 26 weeks 6 days agoBook page
250930 | Cornwall’s 20 mph speed limits have made the roads much safer 28 weeks 2 days agoBook page